Construction Projects
Panoway on Wayzata Bay (Phase 1) – Lake Street (Broadway Ave to Ferndale Rd)
In the last couple of weeks, the contractor has completed the watermain installation along Lake Street from Broadway Ave to Manitoba Ave and is completing the storm sewer and street light systems. Currently, the contractor is placing concrete sidewalks along the north side of Lake Street, and is beginning construction of other features in the new Plaza Park. Sidewalk, trail, street lights, and construction of the new Plaza Park will continue in the coming weeks. Next week,
it is anticipated that westbound Lake Street will reopen to one-way traffic between Broadway Ave and Walker Ave.
Eastbound Lake Street, from Ferndale Rd to Barry Ave, remains to motorists. Westbound Lake Street remains to motorists in this area. Sidewalk and trail construction will continue during the next few weeks.
Lake Street between Broadway Ave and Barry Ave will remain closed through the end of July. Businesses on Lake Street are accessible to pedestrians, and there is ample parking available on adjacent side streets and at the City’s Mill Street Parking Ramp.