Construction of Phase 1 began in the spring of 2020. Construction reached substantial completion on September 11, 2020. Some remaining work includes exterior finishes of the restroom building, the railroad crossings at Barry Avenue and Ferndale Road, and the catenary lighting system at Broadway Avenue. The impact to businesses and residents as crews complete these last items will be minimal and is anticipated to be completed by November 2020.
Click here to read the Navigate Wayzata construction updates.